索引:解釋 These five Process Groups have clear dependencies and are typically performed in the same sequence
on each project. They are independent of application areas or industry focus. Individual Process Groups and individual constituent processes are often iterated prior to completing the project. The constituent processes can have interactions within a Process Group and among Process Groups. The nature of these interactions varies from project to project and may or may not be performed in a particular order.
項目管理過程組
項目管理5大過程組有清晰的相互依賴關係,而且在每個項目上一般都按同樣的順序進行。它們與應用領域或行業無關。在項目完成之前,往往需要反復實施各過程組及其所含過程。個過程可能在同一過程組內或跨越不同過程組相互作用。過程之間的相互作用因項目而異,並可能按或不按某種特定的順序進行。