These diagrams, with activity date information, usually show both the project network logic and the project’s critical path schedule activities. These diagrams can be presented in the activity-on-node diagram format, or presented in a time-scaled schedule network diagram format that is sometimes called a logic bar chart. This example also shows how each work package is planned as a series of related activities.